Under Budget Preparation Menu -> Budget Prep Site Parameters (LG0569) -> Make sure CY*P1 is set to Level 9. Example 25*P1.
The open phases are defined under Phase and Level, and the levels are based on the requisition approval levels.
Under Budget Preparation Menu -> Budget Prep Site Parameters (LG0569) -> Make sure CY*P1 is set to Level 9. Example 25*P1.
The open phases are defined under Phase and Level, and the levels are based on the requisition approval levels.